Shell Turn Around 2022
A major project with 400 workplaces, meeting rooms, sanitary facilities and canteens, various instructional areas, and much more!
Temporary facilities at the factory site
Shell Turn Around 2022 is a major achievement for Algeco in 2022. We installed 17 temporary modular buildings and tents distributed throughout the entire factory with a surface area of no less than 16 km². All this was achieved in just 2.5 months.
In total, more than 400 office spaces were realised, along with various instruction, safety and meeting rooms.
- Project specificaties
-
LocatieMoerdijk
-
Bouwtijd2,5 maanden
-
Aantal unitsxxx
-
Bedrijfstak
360° services
All the rooms were completely furnished and equipped with data connections, WiFi and a fire alarm.
Algeco installed sanitary facilities such as showers and toilets, as well as rest and changing areas, and cafetatia, for the 1,500 technicians involved in the project.